Progress Updates – August 23, 2017 

  • Paving the Ashman to Gordon block is anticipated for Friday, August 25
  • Paving the Gordon to Fitzhugh block is anticipated for the week of September 11
  • Paving the Fitzhugh to Jerome block is anticipated for the week of September 28
  • Timeline Revision – Construction in the Phase 3 area (Rodd to Cronkright) has been postponed until September 5.
    The new plan will close Rodd to Cronkright after Labor Day weekend on September 5 and begin street milling of those blocks on September 6.
  • Rain garden edging installation will begin next week